Sidewalk Progress


Hello Friends and Neighbors!

Our new Miller Street Sidewalk project is proceeding nicely. We are very excited to have this wonderful addition to our neighborhood to bring NoMa closer to City Park, the Salisbury Greenway, and to increase the walkability of our neighborhood.

The curbs were poured this week along W. Miller St. The utility pole, which we reported earlier as being moved, is actually still there with some cables yet connected. We knew there were more utilities on that pole than just Duke Power, such as Time Warner, but can not say why it is taking so long to get both the utilities and the pole moved.

The work on the Jackson St./Lake Rd. sidewalk has also begun. City crews began this work on east end of Lake Rd, are rounding the corner, and working their way north on Jackson along the City Park side of the road. We are thrilled to have this happening as we originally did not anticipate this additional work until sometime next year.